• * Images are for illustration purposes only. Project is in development and may not represent final design.

  • Coach Archie Duran ES

    Colors: Royal Blue, Red, and White

    Mascot: Comets

    Scope of Work

    New 900 student-capacity Elementary Campus

    Demo existing Dowell Elementary

     

    Duran

  • Estimated

    Start Date

    Summer of 2021 

    Expected Consolidation Date

    Fall of 2021 


  • Total Budget

    $28,300,983

    *This total is based on an anticipated project schedule and adjusted for inflation. Project totals may change based on revised project schedules during the course of the five-year bond.


Construction Budget

  • $23,248,851

    *The Construction Cost Limitations (CCL's) for each project are the amounts left for construction once contingency and soft costs have been taken out.  Soft Costs include:  Construction Contingency, Specialty Consultants, Technology & Cabling, Furniture & Fixtures, Movers, Permits, Hazardous Materials and in some cases Portable Costs.

    Budget Breakdown



Project Team

  • Assigned Architect

    Vigil & Associates

    Assigned Contractor

    Aztec Contractors