• Bar

    (Henderson Middle School & Clardy Elementary Consolidation)

  • * Images are for illustration purposes only. Project is in development and may not represent final design.

  • Budget

    $39,118,352

    *This total is based on an anticipated project schedule and adjusted for inflation. Project totals may change based on revised project schedules during the course of the five-year bond.

Construction Budget

  • $29,916,000

    *The Construction Cost Limitations (CCL's) for each project are the amounts left for construction once contingency and soft costs have been taken out.  Soft Costs include:  Construction Contingency, Specialty Consultants, Technology & Cabling, Furniture & Fixtures, Movers, Permits, Hazardous Materials and in some cases Portable Costs.

    Budget Breakdown

  • Scope of Work

    New Building Additions

    • Middle School Classrooms
    • New Library, new fine Arts, new administration
    • New Middle School Gym

    Renovations to Existing Henderson

    • Demolition of Administration Building
    • HVAC Upgrade to Refrigerated Air to building C&D (Academic Buildings)
    • New Electrical Systems to building C&D (Academic Buildings)
    • Aesthetic Upgrades to building C&D (Academic Buildings)
    • Minimal upgrades to existing Gym & Cafeteria

     

     

Project Team

  • Assigned Architect

    Mijares-Mora Architects

    Assigned Contractor

    Dantex Construction

  • Tinajero

  • Estimated Completion

    Fall of 2022 


  • MASCOT TBD


  • Colors

  • Tinajero